Snorre Export Topside and Robustness contract to Aibel

Statoil has awarded Aibel a modification contract for the Snorre A and Snorre B platform. The value of the contract is approximately MNOK 400.
The scope of the contract is engineering, procurement, fabrication and installation of major modification work on the Snorre platforms related to Snorre Export and Robustness.
A detailed description of the scope of work:

Snorre A

* Modifications to Vigdis 3rd stage separator/ prod. water transfer
* Snorre A oil export to Snorre B, new pig launcher, piping and valves
* Snorre A preparation for new riser
* Fiscal metering bypass with new flow meter
* New export pump for oil export to Snorre B
* Vigdis x-over, new crossover pumps and flowmeter

Snorre B

* Snorre B oil import from Snorre A, module sections with equipments
* New oil import gas-to-oil heat exchanger
* Preparation for new oil import riser
* Snorre B reuse of existing oil steam heater (not been in use before)

In addition there are several possible options in this contract.

‘We are grateful for the confidence Statoil has shown us by awarding this contract to Aibel, says Jan Skogseth, President & CEO of Aibel. 'Our focus will, as always on complex projects like this, be on HSE and good project execution, in close cooperation with our client.’

The contract has a relative long duration, with start up of engineering immediately and commencement of offshore work in February 2011. The project duration will be for a period of approximately three (3) years, conducted in parallel with full operations on the platform. The project will be executed out of Haugesund.

‘I take this opportunity to thank and congratulate Roar Jørgensen and the rest of the tender team for their great efforts to secure this contract. Simon Røksund is our nominated project manager for this contract,’ says Nils Arne Hatleskog, SVP Modifications.

The manning level for Aibel will be about 100 people and the project will report to business unit Modifications.

Signing of the final contract documents is scheduled for March 2010.